Timing monthly claim checks so certification still works

A verification memo that arrives after you have already certified payment is only a historical note.

City skyline of modern towers under soft daylight

Monthly progress claims follow a clock: contractor cut-off, review window, certification, payment. Cost audit coordination has to sit inside that clock, not beside it.

Agree the cut-off in the engagement letter

We set the claim receipt date and the memo deadline before the first month. Without those two dates, everyone improvises — and improvisation favours the late claim.

Sample the site, do not remeasure the building

Payment verification is not a full remeasure unless you have hired us for that. Spot checks on high-value work and materials-on-site schedules usually surface the issues that matter for certification.

Separate arithmetic errors from commercial arguments

A wrong retention percentage is a correction. A disputed entitlement is a commercial decision. Mixing them in one paragraph slows the certifier. We keep them on separate lines of the memo.